South Hinksey sewer flooding

We held a meeting on 20 August 2015 to discuss this, especially in relation to possible temporary bunding of the village at time of river flooding.

Representatives from Thames Water (TW), the Environment Agency (EA) and of OFA from South Hinksey met. We had an interesting and fruitful discussion. These actions were agreed:

Thames Water (TW) to initiate a clean of the box culvert north of the village (by today, 27 Aug, this has already been ordered) and update us further on the work that has been, and still is being, done to considerably improve the pumping station at Littlemore.

TW will consider OFA’s suggestion of a sewer bypass for the village, as part of the ongoing Oxford Catchment Study.

Adrian Porter for OFA will fit a chain and handle to the existing non-return flap valve on the Manor Road surface water outlet to enable manual override if necessary.

The suggestion of a memorandum of understanding between the EA and TW, as to how sewer flooding would be dealt with at times of fluvial flooding, especially if a temporary bund were deployed, will be taken forward by the EA.

Many thanks to Thames Water and the Environment Agency for meeting with us and their very positive approach to the problems.