Seacourt P&R – Key Point 5: Green Belt

The proposal is inconsistent with both national and local Green Belt policy:

  • The site is in the Oxford Green Belt where the presumption is that development is inappropriate. Preservation of ‘openness’ is a key objective of Green Belt policy, The NPPF places great emphasis on it. Attempting to hide the development from view by landscaping does not constitute preserving openness.
  • The proposal will also clearly breach Oxford City’s own Core Strategy key policy CS4 for the protection of Green Belt land.

 

Seacourt P&R – Key Point 4: Oxford City’s Planning Strategy

cs2

Within Oxford City Council’s main strategic planning document, the Core Strategy, Core Strategy 2 (CS2, see above) states:

‘Greenfield land will not be allocated for development if any part of the development would be on Flood Zone 3b.’ 

Our comment: The proposed site for the new car park is greenfield, and in functional Flood Zone 3b.

CS2 also says that ‘development will only be permitted on greenfield land if it is specifically allocated for that use in the [Oxford City Council’s] Local Development Framework’.

Our comment: This site is not so allocated.

Core Strategy 11 (CS11) says:

‘Planning permission will not be granted for any development in the functional flood plain (Flood Zone 3b) except water-compatible uses and essential infrastructure.’

Our comment: The proposed site is neither ‘water-compatible’ (a category intended for developments such as marinas), nor ‘essential infrastructure’ (which includes projects such as water treatment works, or roads which have to pass through a floodplain).

In our view the position could not be clearer – this proposal is, in fact, precisely the kind of development that the Council’s own strategic planning policy is there to prevent.

Further comment on Network Rail’s planning application for track-raising

We submitted our comments on the latest revision (A02) of Network Rail’s flood risk assessment (FRA) for their planning application for track-raising yesterday.

The planning application is number 15/03703 and details can be found on Oxford City Council’s planning portal https://www.oxford.gov.uk/info/20066/planning_applications/328/view_and_comment_on_planning_applications

The application is going to West Area Planning Committee for determination on 3 May at 2 pm at the Town Hall.

See also our earlier post https://oxfordfloodalliance.org.uk/2016/03/28/network-rails-planning-application-for-track-raising/

Network Rail’s planning application for track-raising

Network Rail (NR) has applied for planning permission in relation to its plan to raise a particularly low area of the mainline track to London, beneath and either side of the old Abingdon Road bridge (Redbridge) near Kennington, to reduce the risk of the line flooding. Doing only this would increase the risk of flooding to the west of the line by raising the height of what is already a dam to the free flow of flood water. So NR propose a new culvert beneath the railway to compensate for this.

We have no objection to this plan in principle, but it must be done properly to ensure that the flood risk to properties and roads is not increased. If the mitigating culvert is too big areas to the east would be affected, too small and those to the west would suffer.

NR then need to convince the planning authority that their proposal gets the balance right and does not increase anyone’s flood risk. This is done mainly by modelling of flood flows and levels and reporting the results as part of a Flood Risk Assessment (FRA) which is at the heart of the planning application. This was first submitted in February. We went over this with a fine-tooth comb and found gaps and serious inconsistencies in the data presented. We did not believe that the document allowed the necessary judgement to be made, indeed it raised more questions than it answered. We made a submission to the planning authority, Oxford City Council, suggesting that, on the available evidence, it would be unwise to allow the application. The FRA, our comments, and many other documents can be seen on the council’s planning website – application number 15/03703/FUL. Our comments: OFA comments on 15/03703/FUL – Construction of a culvert.

A revised FRA (Revision AO1) was tabled by NR on 25 February in response to comments made by the Environment Agency to them. Because of the timing this revision  did not deal with our questions. We submitted further comments on AO1, reiterating and expanding on key points, on 9 March. We again gave our opinion that the evidence presented in the FRA was such that it could not allow a safe and proper decision to be made. This submission: 15:03703:FUL OFA Comments on the revised FRA (revision AO1, Feb 2016) F

After making our second submission to the planners we met with representatives of NR and their advisers. They confirmed that there were indeed the errors we had drawn attention to, in both the original and AO1 revision of the FRA. They said they had identified the reason for these errors and explained this. We understand that they will be filing a further revision, plus an amended version of an associated document, GRIP3, which is referred to in the FRA.

We have discussed our concerns with the planning officer at the Council who has been helpful and attentive to our arguments. A decision on the application has now been deferred to allow time for the revised documents from NR to be reviewed by the public and by Council planning staff.

Postscript: we were later asked to review the maps associated with the FRA, to compare what the model suggested with what we know ‘on the ground’. Our comments: 15:03703:FUL – OFA Review of flood model maps.

Working to reduce sewer flooding

Simon Collings represented OFA at the second meeting of Oxford City Council Scrutiny Panel on sewer flooding. Thames Water (TW) gave an update on where they are with a) Grandpont and b) the Oxford Catchment Study:

At Grandpont they have identified the most likely causes of sewer flooding and TW will now work with the City Council and residents to improve things. Local resident Brian Durham of OFA and SOFAG has been closely involved in this work.

On the Catchment Study they are engaged in two parallel processes:

  • a physical inspection of assets across the city – with any issues they identify being fixed as they go along (where the business case is obvious). This includes an inspection of both main trunk sewers.
  • customer surveys to help them understand where problems arise during a flood and how these manifest themselves.

So far they haven’t encountered anything which would suggest they need major capital investments, though they do plan to upgrade the pumps at Littlemore.

TW are talking to the Environment Agency (EA) team working on the Oxford Flood Alleviation Scheme, and the two modelling teams are going to share data and work together. By good luck the option development phases of both projects are working to similar timetables. EA will help TW understand how the river flooding affects the sewers, and TW will contribute to that work.

There will be one more meeting of the Scrutiny Panel in November/December but from then on formal reports will be given through the Oxford Area Flood Partnership, to avoid duplication of meetings.

Oxford & Abingdon Scheme

We attended a ‘Councillor Update’ on the scheme at County Hall last evening. Cllr Rodney Rose introduced the evening, followed by contributions from the Environment Agency, Oxford City Council, Vale of White Horse District Council and the Local Enterprise Partnership (LEP). There was a good attendance from councillors, and plenty of questions and discussion after the presentations.

Maintenance meeting

Peter Rawcliffe of OFA met with Peter Collins of the Environment Agency today. Discussion was to take forward proposals to get riparian owners to undertake maintenance of local waterways.

Ownership maps will be shared;  a site visit was arranged for 19 March to the Coldharbour area of Hinksey Stream where there is serious, longstanding, obstruction; we hope a representative from Oxford City Council will be able to attend too.