Since our last update in February this year we have seen further steady progress on the Oxford Flood Alleviation Scheme (OFAS), designed to reduce flood risk for hundreds of properties in Oxford and nearby. We have been involved in several ways:
  • As part of the Sponsoring Group, the body representing the various partners in the scheme and having overall responsibility for it.
  • Urging that maintenance be provided for in perpetuity rather than just 10 years. We have proposed setting up a dedicated body to be responsible for this; this idea has received good support. We are discussing with the Environment Agency and partners other possible approaches, and if an independent body, what corporate structure might be best.
  • We have been working with the Freshwater Habitats Trust and the Environment Agency to try to ensure that the scheme (while it will regrettably involve some environmental losses) can incorporate significant environmental enhancements too, including the important freshwater habitat.
  • We are supporting the EA if their efforts to close the funding gap for the scheme – currently at $4m. This money needs to be found by the end of November if the scheme is to go ahead.
  • We have participated in a number of public consultation events about the route of the scheme.
OFAS is running to schedule, and assuming the money is found the next major step is application for planning permission, probably in spring 2018.
 
Local matters
Earl Street has a new, dedicated, mobile pump that will be available to them in the event of future floods. Nick Hills, an Earl Street resident and member of our Steering Group, applied successfully for a generous grant, £20,000, from Scottish & Southern Electricity Networks.
South Hinksey groundworks have been completed, meaning the village is now ‘temporary barrier ready’ when floods next threaten. Many thanks to the Vale of the White Horse District Council for funding and to the Environment Agency, especially engineer Magnus Williams, for all the hard work that’s made this happen.
Both areas can now look forward to the coming winter with more confidence.
Seacourt Park & Ride
As reported previously we opposed the application by Oxford City Council to extend this P&R into the flood plain. The application did not, in our view, show that flood risk would not be increased. We believe that a revised application will be advertised at some point and we will scrutinise this with care. The timeframe for this is currently not clear.
Local MPs
Following the elections this year we have two new MPs, Anneliese Dodds for Oxford East, and Layla Moran for Oxford West & Abingdon; we are in the process of meeting and briefing them on flood related matters. Both MPs are supportive of the need for a flood scheme.
OFA Steering Group

OFAS: funding gap

The Oxford Flood Alleviation Scheme (OFAS) Sponsoring Group met earlier this month. This group provides high-level oversight of the project and is made up of representatives from the several partner organisations. One topic discussed was the shortfall of £4 million of the £121 million cost of the scheme. As the local ‘grass roots’ community organisation we’re now exploring ways we might engage support from local businesses.

OFAS: archaeological investigations

Further archaeological investigations are starting soon in the OFAS area, with digging of trenches in places identified from previous work as being of potential interest. Teams are due to begin setting up base camp in Manor Farm, South Hinksey today. The work is expected to be completed in November 2017.

See this Archaeology Information Sheet for more details.

OFAS – Public Consultation about to begin

Public consultation on the Oxford Flood Alleviation Scheme, OFAS, begins tomorrow.

See https://www.gov.uk/government/consultations/oxford-flood-alleviation-scheme-design-consultation for more about this, and tomorrow the dedicated consultation website should be available from the link there.

 

 

Visit by EA Chair

We joined Emma Howard Boyd, Chair of the Environment Agency, the OFAS Project Team and other partners when Emma visited Oxford today. The Public Consultation for the Oxford Flood Alleviation Scheme is due to be launched in two days time, on Friday 23 June.

OFAS: Environmental meeting

Attended an environmental update meeting yesterday, organised by the EA with a number of local environmental stakeholders attending. A lot of thought is going into making the most of possible environmental enhancements that the Scheme can bring.

Led by Penny Burt of the Environment Agency we covered surveys, ecological trial areas, archaeology, low-flows and existing watercourses, fish passage, Hinksey Meadow, trees and bridges, habitat creation and access. Also mentioned was future maintenance – we felt that the plans were not nearly long-term enough and this was discussed.

For our part we are working closely with the Freshwater Habitats Trust. The Oxford area is rich in freshwater species, though there is, nevertheless, a long term decline: this Scheme could help reverse that trend. We’d like to give the public, including school children, a chance to be involved, including with data collection in the field – sometimes called ‘citizen science’.

The damselflies in the photographs are closely associated with the freshwater habitat.

Seacourt P&R in the Oxford Mail; smart signs, plus risk to life

This article in the Oxford Mail talks about the possibility of  ‘smart signs’ – electronic boards – on the ring road, to alert drivers to where there are empty park and ride spaces around Oxford. This could obviate the (claimed) need to increase the number of spaces at Seacourt, instead pointing drivers to (say) nearby Redbridge. According to an earlier report in the Oxford Mail there is apparently so much spare capacity at Redbridge that the City Council proposes to remove 270 parking spaces, and is quoted in the newspaper as saying that the loss of these spaces would be ‘marginal’.

It seems to us to be inconsistent for the City Council to argue that removing 270 spaces at Redbridge is perfectly ok, while at the same time arguing a burning need to build new spaces at Seacourt – in the floodplain, on Green Belt land, contrary to local and national planning guidance and, as far as the present application goes, creating a potential risk to life (see towards the end of the first newspaper article and our previous post). Never mind the cost, which has already risen from about £2million to over £4 million.