This update has recently been sent to those on our mailing list.

Dear OFA contact,

We last sent out an update in Oct 2019, just after the news about the problems with the A423 bridge (southern bypass) and likely delays to the Oxford Flood Alleviation Scheme (OFAS). OFA is still active and has been participating in meetings of the Sponsoring Group for the OFAS scheme and has also held separate meetings with the Environment Agency team about water course maintenance since our last update.

Despite the A423 issues, and the challenges presented by coronavirus, the OFAS scheme continues to progress. The EA and the County Council have agreed a collaborative approach to replacing the A423 bridge and constructing the OFAS scheme. This should save on costs for OFAS, and reduce the level of maintenance required in future.

The EA withdrew the original planning application earlier in the year and is currently revising this to incorporate the new A423 arrangements, and to update the documents on some other aspects of the scheme. Once these are resubmitted to the planning authority the public will have a fresh opportunity to comment on the plans. The EA is continuing to meet with objectors to the scheme with a view to trying to address outstanding areas of public concern.

Because OFAS is now expected to be delivered two years later than originally expected it is important that effective flood response procedures are in place in case a major flood event happens in the next few years. The EA, Fire Brigade and the local Council officials will be holding a practice response on 20 August to test aspects of current procedures. Because of coronavirus these will not involve the pubic.

The text of a recent update from the Environment Agency is pasted below which provides some additional information on OFAS and other matters,

OFA Steering Group

Oxford Scheme update

A423 bridge replacement

Oxfordshire County Council began the propping work on the A423 Kennington Railway Bridge in July.

Replacement of the A423 Bridge has provided an opportunity to design and build the bridge and the flood scheme together. This allows us to reduce disruption during construction and ensure the best use of public money. The updated design will use open channels instead of culverts to allow the flow of floodwater under the bridge. This will provide a better environment for wildlife and requires less maintenance.

The bridge is at the southern end of the scheme and during a flood, water would need to pass underneath it to re-join the River Thames. This capacity needs to be in place before the scheme is constructed to avoid increasing flood risk elsewhere. We also need to have all approvals, including planning permission and our Compulsory Purchase Order secured.

South Hinksey Archaeology

If you’ve been walking near South Hinksey, you may have spotted our contractors on site. We are carrying out archaeology surveys in a field near South Hinksey village to check whether the area is suitable for us to use as the main compound for when we construct the scheme. The archaeology surveys will determine whether there are any historical artefacts in the field. We want to ensure there’s no risk of us damaging any artefacts or remains. Once we have finished the investigations, we will remove our equipment from the site and reinstate the fields.

Kendall Copse Ground Investigations

To complement the new A423 bridge replacement, we are reviewing the design of the scheme around Kendall Copse, near Kennington.

From 10 August, we will be digging trial pits and drilling boreholes to understand the ground conditions beneath the site in order to finalise these designs.

Oxford Flood Incident Exercise

To ensure our flood protection plans are well-tested, the Oxford Flood Alleviation Scheme partners and emergency responders will be practicing their incident response plans on 20 August 2020.

The flood response exercise will consist of:

 •temporary flood barriers in South Hinksey and Bullstake Close

•pumps to remove flood water along Botley Road

Due to the current Government guidance on public gatherings, we won’t be able to invite members of the community to attend. We will be sharing updates on Twitter and Facebook as the exercise progresses. We will also share video footage of the temporary barriers and pumps so you can see our field teams in action.

Managing your flood risk

During the summer months, flood risk might be low on your list of priorities, but Environment Agency officers are thinking about it year-round. Throughout the year our operations staff carry out inspections and clear debris to keep main rivers moving. To report a blockage that could cause flooding call our 24 incident hotline: 0800 80 70 60.

You can also find out what maintenance is planned in your area: environment.data.gov.uk/asset-management/index.html

Stay prepared by signing up for flood alerts and preparing a flood plan: https://flood-warning-information.service.gov.uk

  

Want to know more?

If you have any questions or want to be added to our mailing list, please contact us at: OxfordScheme@environment-agency.gov.uk

A mistake

While we wait anxiously to see whether homes, businesses and roads will flood, work on the City Council’s extension to its Seacourt Park & Ride has come to a very wet standstill.

Building a car park in a flood plain is not sensible. Work having started as the wet winter season approached, the site is now a lake and work has stopped. The JCBs have been withdrawn onto the higher ground of the existing car park, and heaps of building materials are abandoned in the water. If the construction had been completed much of the extension would currently be under water. All this while the City is on ‘only’ a Flood Alert, the lowest category of concern.

The construction costs are likely to be much higher than estimated because of the disruption caused by flood events of the kind we’re currently witnessing. Councillors ignored the reality of frequent flooding here when they approved the planning application, and now we’re seeing the consequences. The last official budget figure we’re aware of was around £4million; we have heard, from a usually reliable source, that the cost may have risen to around £6 million, even before the present flooding of the site. Is this a sensible use of tax payers’ money?

Flooding at the site began on  Monday, so it’s already been a working week that it would have been out of action if it had been built – that means lost revenue and an unreliable service. And time and money would then be needed for pumping out, clearing up and very likely making repairs before the extension could be safely reopened to the public. Further expense and further loss of revenue. Because the site is so low-lying, this will happen quite often.

Because it’s a car park and not a field there is increased risk to the public and to vehicles, and it remains to be seen how well the Council is able to manage flooding here. The water came up quite quickly at the start of the week, and in the interests of safety the extension would have had to be closed before that to avoid cars getting trapped in flood water, i.e. sometime early last week. And remember we are only on a Flood Alert, not a Flood Warning. Were people to try to enter even quite shallow floodwater to retrieve their cars things could go horribly wrong.

In the second photo above, from yesterday, you can see two large pipes floating in the lake, one in the centre, the other far over to the right against the boundary fence. If the flooding worsens these could float downstream and jam under the nearby bridge under the Botley Road, exacerbating flood risk. Were it already a car park, for pipes read cars.

We, and many others, fought this ill-conceived project hard. We hope the City Council will even now abandon it and restore the site to its previous state, as a valuable wildlife habitat, including for the badgers who have been driven out. To press on regardless means wasting ever more of Oxford’s citizens’ money, putting off for years any possible financial return to the Council, and meanwhile potentially both increasing flood risk and posing a risk to life and vehicles.